
The Hydro-Québec mandate given to our team consisted of installing three new 120 kV lines from the Montérégie substation, strengthening the regional electrical transmission network.
For the project, our team blasted more than 8,000 m³ of rock to make room for the concrete structures. The 181,000 m² substation platform required more than 450,000 mt of backfill material (transported by truck).
Approximately 5 km of prefabricated cable conduits were installed on the substation platform and about 200 km of cable connected all the equipment.
We did extensive site preparation and grading.
We hired a specialized firm to ensure that the noise level of on-site heavy vehicles remained within the permitted limits.
We performed the work efficiently, despite the heavy traffic and management of the signal system at the site’s perimeter.
181,000 m2
450,000