Hydro-Québec Appalaches substation

Client
Hydro-Québec
Sector
Energy
Delivery mode
Lump Sum
Location
Thetford Mines, QC, CA
Year built
1996
poste_appalaches

Power station construction

Hydro-Quebec awarded us the mandate to build the Appalaches substation, a 735 KV station in Thetford Mines.


We completed the project in three phases. Phases I and II included the following work:

  • Building a road linking the site to the main road
  • Site leveling
  • Site profiling
  • Site drainage
  • Building the station’s exterior foundations 
  • Building three buildings

Phase III included the installation of these elements:

  • High-voltage equipment
  • Insulators
  • Circuit breakers
  • Selectors
  • Surge protectors
  • Current transformers
  • Wiring
  • Controls
  • Instrumentation

The entire project required 6,600 m3 of concrete, 3,000 anchor bolts and 5.5 km of chain-link fencing.

Despite the magnitude of the project and the challenges posed by significant ground elevation changes, we completed the project in accordance with the client's requirements—and on schedule!

Our challenge

Major excavation & filling

We carried out major excavation and filling work to level the ground, which could vary in elevation by as much as 30 m in some places.

Site facts & figures

209,000 m3

of excavated material

450,000

tonnes of backfill