LG-1 Hydroelectric Generating Station

Client
Hydro-Québec
Sector
Energy
Delivery mode
Lump Sum
Location
James Bay, QC, CA
Year built
1992
hydroélectrique, Baie James

Hydroelectric power plant, dike & dam

Our team completed this project five months ahead of schedule, building a 1,368 MW run-of-river hydroelectric power plant in James Bay based on strict environmental criteria.


The project involved the construction of these components:

  • A dike
  • A transitional dam
  • A gravity dam
  • A concrete sectional gravity dam to support a 45 m spillway equipped with eight floodgates
  • A 330 m x 60 m x 60 m power plant

The geometry for the construction was particularly intricate, requiring multiple sets of formwork in light of the mandate’s short time frame. Most of the formwork, which covered 290,000 m² in total, could be prefabricated at a lower cost on site.

During this project, we cast in place 401,000 m³ of concrete, used 19,000 tonnes of rebar, installed four rail-mounted tower cranes and poured a record-breaking 10,500 m³ of concrete in a single day.

By deploying equipment and personnel 20 to 24 hours a day, six or seven days a week, we completed the project in 48 months, despite a particularly tight schedule.

Our challenge

Meeting strict criteria

We followed the strict compliance requirements of a particularly stringent environmental regulation, right to the letter.

Site facts & figures

10,500 m3

of concrete poured in a single day

19,000

tonnes of rebar