The Town of Gander awarded the entire mandate in self-performed work mode to build a pumping station and a wastewater treatment plant, including an operations and chlorination building, plus four outdoor gravity lagoons, each measuring approximately 65,532 m2.
This major project replaced two existing wastewater treatment plants.
In the operations building, there is a workroom that serves as the entrance to the building for raw wastewater. In this room, a screen system filters, removes and stores large waste.
The remaining wastewater passes through the screen to the four lagoons, where it is treated by a fan diffusion system. Next, the water enters the UV disinfection room, where the TrojanUV performs the final treatment. At this point, the water finally exits the building and flows into Gander's Whitman Pond.
We completed the project quickly and efficiently, keeping operating costs under the client's budget.
We designed a wastewater treatment system, keeping operating costs below a specified budgetary threshold.
We completely removed and replaced the peat bog on the site with suitable backfill.
65,532 m2
4