Moncton Wastewater Treatment Plant TransAqua

Upgrades, Construction and Improvements

We were awarded the contract to upgrade the TransAqua GMWC wastewater treatment facility.


The project included the following work:

  • Upgrading the primary treatment facility
  • Building two new grit chambers and four additional primary clarifiers
  • Building a new primary clarifier building
  • Installing new miscellaneous equipment
  • Adding electrical and mechanical facilities (including an additional electrical room)
  • Making improvements to building
  • Building a new sludge reception building
  • Replacing bar screens and grit classifiers

We were also responsible for the following aspects of the project:

  • Developing the performance criteria and the FTP study
  • Preparing, implementing and following up the project management plan and project-specific quality plan
  • Planning the design and construction activities
  • Managing professionals from disciplines
  • Budgeting and value engineering
  • Controlling costs, schedules and quality
  • Procurement and site supervision
  • Training
  • Construction, methods and logistics
  • Coordinating and installing equipment
  • Commissioning and warranty follow-up
  • Purchasing permits and licences