Taschereau and Highway 10 Interchange Reconfiguration
Transportation
Brossard, QC, CA
Our team was awarded the mandate to build, repair and rebuild the Highway 20/30 interchange in Boucherville.
Despite a tight schedule, a high-traffic site and specialized work, we completed the project efficiently and accurately within the stipulated timeframe.
Traffic was constant in the work area, making the site very busy.
Our own teams carried out extensive work in various specialties, such as building retaining walls, installing driven piles, earthwork, drainage, formwork and casting concrete.
We completed the mandate within the client’s strict timeline.
100,000 m3
300,000